Based on the following sensitivity report, how much should the firm be willing to pay for 75 more units of Resource_C? V

Posted: Fri May 20, 2022 6:32 am
by answerhappygod
Based On The Following Sensitivity Report How Much Should The Firm Be Willing To Pay For 75 More Units Of Resource C V 1
Based On The Following Sensitivity Report How Much Should The Firm Be Willing To Pay For 75 More Units Of Resource C V 1 (21.78 KiB) Viewed 54 times
Based on the following sensitivity report, how much should the firm be willing to pay for 75 more units of Resource_C? Variable Cells Objective Coefficient Allowable Increase Cell $B$2 $B$3 $B$4 2 Final Value Reduced Cost 0 -2 175 © 0 -1.5 Name Product 1 Product 2 Product 3 5 7 9 Allowable Decrease 1E+30 1 1E+30 1E+30 1.5 Constraints Shadow Price 0 Constraint R.H. Side Cell $H$9 $H$10 $H$11 Final Value 0 525 700 Name Resource A Resource_B Resource C Allowable Increase 1E+30 1E+30 180 100 800 700 Allowable Decrease 90 340 79 0 1.21 (Round your answer to 2 decimal places.) Units of Resource_C