The following table provides the information necessary to construct a project network diagram and project crash data: a.
Posted: Fri May 20, 2022 6:05 am
The following table provides the information necessary to construct a project network diagram and project crash data: a. Crash the project until no more crash can be performed b. How much it would cost c. The new critical path(s) Activity Immediate predecessor A 84 9 B2 се D E F2 A A Activity Time (weeks) Normale Crash 16 14 8 64 52 42 42 2 60 4 10 72 152 10 Activity Cost ($) Normale Crash 2000 4400 1000 1800 500 700 600 1300 1500 3000 800 1600 3000 4500 5000 8000 ве B ce DE F, G, He He End ܒܟ