Example 4/A 250 MW powers stations delivers 200 MW for 2 hours, 150 MW for 8 hours and is shut down for the rest of each
Posted: Thu May 19, 2022 12:39 pm
Example 4/A 250 MW powers stations delivers 200 MW for 2 hours, 150 MW for 8 hours and is shut down for the rest of each day. It is also lubrication for 14 days and shut down for maintenance for 60 days each year. Calculate its annual load factor. 126.6%