1 pts Question 39 3. The following 4-step process is used for fulfing an order. This process is staffed by two workers W
Posted: Thu May 19, 2022 6:50 am
Question 39 3. The following 4-step process is used for fulfing an order. This process is staffed by two workers Worker A performs the first two Steps and worker B takes care of the last two steps. Each worker is paid $20 per hour. Cycle time of this process (assuming this process works at full capacity is STEP 1 STEP 2 STEP 3 STEP 4 1 min.lorder 3 min./order 3 min./order 3 min./order DA 20 IS D 01 Question 40