Question 40 1 pts 11. The following 4-step process is used for fulfilling an order. This process is staffed by two worke

Posted: Thu May 19, 2022 6:50 am
by answerhappygod
Question 40 1 Pts 11 The Following 4 Step Process Is Used For Fulfilling An Order This Process Is Staffed By Two Worke 1
Question 40 1 Pts 11 The Following 4 Step Process Is Used For Fulfilling An Order This Process Is Staffed By Two Worke 1 (24.17 KiB) Viewed 37 times
Question 40 1 pts 11. The following 4-step process is used for fulfilling an order. This process is staffed by two workers: Worker A performs the first two Steps and worker takes care ut the last two steen. Each worker is paid $20 per hour. What is the takt time of this process in minutes if this process has actual output of 120 units in twenty hours! STEP 1 STEP 2 STEP 3 STEP 4 1 min./order 3 min./order 3 min./order 3 min./order OS 10 OD O