Question 15 1 pts ORS Corp. is designing a product Layout for a new product. They plan to use this production line 10 ho

Posted: Thu May 19, 2022 6:44 am
by answerhappygod
Question 15 1 Pts Ors Corp Is Designing A Product Layout For A New Product They Plan To Use This Production Line 10 Ho 1
Question 15 1 Pts Ors Corp Is Designing A Product Layout For A New Product They Plan To Use This Production Line 10 Ho 1 (31.16 KiB) Viewed 25 times
Question 15 1 pts ORS Corp. is designing a product Layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product Task Timesecs) Immediate Predecessor 34 none b 20 10 d b 10 c 1 24 10 1 Without considering forecasted demand, what is the minimum possible cycle time for this production line Assume you can hire only one person for each taske conde O 10 seconds