Noble Tech is considering the following project. The estimated cost of the project in the current ye is $767,000. The project is expected to generate cash flows in the amount of $361,000 in the first and second year, followed by $1,300,000 in year 3 through year 5. No cash flow is expected after year 5. The company uses a discount rate of 14.8% for similar projects. Calculate the NPV of this project. (Round your answer to the nearest dollar).