Page 1 of 1

Create a precedence activity network using the following details: Activity Duration (in days) Precedents A 4 B 3 С 5 B D

Posted: Wed May 18, 2022 4:17 pm
by answerhappygod
 1
1 (120.51 KiB) Viewed 35 times
Create a precedence activity network using the following details: Activity Duration (in days) Precedents A 4 B 3 С 5 B D 6 E, A IE 3 A, F 2 D G G 5 E Н 18 G Assume that the project starts from Day 0. Apply the critical path method by doing the forward and backward passes, Enter the FLOAT associated with each activity in the boxes below. Make sure you check your answers carefully. Incorrect answers will receive O mark. 1. Task A 2. Task B 3. Task C 4. Task D 5. Task E 6. Task F