A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Projects -$1,0
Posted: Tue Nov 16, 2021 8:05 am
company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Projects -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $5 $260 $380 $796.31 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A