Page 1 of 1

A project cost 80000 is expects to generate cash flows are given as follows.@10% Year 1 2 3 4 5 CF 15000 6000 7000 PV fa

Posted: Tue Nov 16, 2021 7:33 am
by answerhappygod
A project cost 80000 is expects to generate cash flows
are given as follows.@10%
Year
1
2
3
4
5
CF
15000
6000
7000
PV factor
0.893
0.792
0.712
0.636
0.567
Calculate the NPV and justify whether the project is
recommended or not.