A project has a contract price of $3,660,875. The cost to date is $1,194,339 and the estimated cost to complete is $2,01
Posted: Mon May 16, 2022 12:19 pm
A project has a contract price of $3,660,875. The cost to date is $1,194,339 and the estimated cost to complete is $2,019,613. Based on this information, calculate the total gross profit recognized to date. Report your answer to the nearest dollar 446,923