You have the following information about an office project: Contract (original contract amount): $5,500,000 Cost to Date

Posted: Mon May 16, 2022 12:19 pm
by answerhappygod
You Have The Following Information About An Office Project Contract Original Contract Amount 5 500 000 Cost To Date 1
You Have The Following Information About An Office Project Contract Original Contract Amount 5 500 000 Cost To Date 1 (38.22 KiB) Viewed 51 times
You have the following information about an office project: Contract (original contract amount): $5,500,000 Cost to Date: $3,500,000 Estimated cost to complete: $1,750,000 Calculate the following to the nearest dollar or 0.1% Current Estimated Total Cost Estimated Profit or Loss at Completion Percent complete Total Profit or Loss to Date