ample 2 concreting Operation: Quantity of concrete to pour: 500 ft3 Normal work hours: 8 hours/day Overtime rate = 1.5 o
Posted: Mon May 16, 2022 9:09 am
ample 2 concreting Operation: Quantity of concrete to pour: 500 ft3 Normal work hours: 8 hours/day Overtime rate = 1.5 of the normal rate Productivity during an overtime hour = 90% Cost of ready-mixed concrete (M12) = $17/ft3 Find the total time & cost required to finish the job using both methods of construction - Labor LI Description General Laborer Concrete Worker Rate S/hr 15 Equipment E2 Description Crane & Bucket Pump & Tool Rental S/hr Operational S/hr 40 10 15 5 L4 25 E14 Crew C16 Description Concrete Crew Output/Day 100 Unit ft Composition 2L1 + 3L4 + 1E2 +2E14 Resources Method of Construction Method 1 Method 2 Description Concreting by Pump (8hrs/day) Concreting by Pump (14hrs/day) Unit ft At 1 C16+ M12 1 C16+ M12 5 Lecture 9 Construction Management