Complete the ES, LS, EF, LF, FF & TF for each node on the healthcare exam room remodel schedule: ETCM 4010 Spring 2020 F
Posted: Mon May 16, 2022 9:05 am
Complete the ES, LS, EF, LF, FF & TF for each node on the healthcare exam room remodel schedule: ETCM 4010 Spring 2020 Final Node Question.pdf $ If you can't open/view the above attached file: [Activity - Duration (Predecessor)] Notice to proceed - 0 Order & Deliver Materials - 10 (NTP) Set-up Negative Air Pressure Machines - 1 (NTP) Verify Electrical Services - 1 (NTP) Set-up Hand Wash Station - 1 (NTP) Remove Existing Finishes - 5 (Set-up Negative...; Hand Wash...) Replace Existing Light Fixtures - 2 (Set-up Negative...; Verify Electrical...) Paint Walls - 1 (Remove Existing...; Replace Existing Lighting...) Install Ceiling Tile - 1 (Materials. Paint Walls; Replace Existing Light...) Install Nurse Station - 1 (Install Ceiling Tile) Install Sink - 2 (Install Nurse Station) Final Touch-up Paint - 1 (Install Nurse Station) Final clean space - 1 (Final Touch-up Paint) Demobilize/ Complete - 1 (Final Touch-up Paint)