Determine the bid price for a project that you are estimating has the following itemized costs Direct Labor Cost - $200,
Posted: Mon May 16, 2022 9:02 am
Determine the bid price for a project that you are estimating has the following itemized costs Direct Labor Cost - $200,000 Direct Material Cost - $350,000 Direct Equipment Cost - $200,000 Sales Tax - 8% Markups & other add-ons - $150,000 $928,000 $972.000 $960,000 $944.000