1. A. Conduct forward and backward pass and determine ES, EF, LS, LF, TF, and FF for the following network. Also identify the critical activities and critical paths. No need fill out the table. However, for Part B, it is required to show the FF calculations. (50 Points) ES EF Activity (Dur) LS TF FF LF A (2) D (7) G(3) J (7) M (3) B (1) E (6) H(7) K(5) N (5) C(2) F(3) 1(8) L (3) 0(3)