(c) A dam shown in Figure Q1 (c) retains 6m of water. A sheet pile wall on the upstream side (which is to reduce seepage

Posted: Mon May 16, 2022 7:46 am
by answerhappygod
C A Dam Shown In Figure Q1 C Retains 6m Of Water A Sheet Pile Wall On The Upstream Side Which Is To Reduce Seepage 1
C A Dam Shown In Figure Q1 C Retains 6m Of Water A Sheet Pile Wall On The Upstream Side Which Is To Reduce Seepage 1 (97.51 KiB) Viewed 43 times
(c) A dam shown in Figure Q1 (c) retains 6m of water. A sheet pile wall on the upstream side (which is to reduce seepage under the dam) penetrates 4m into a 10m thick of silty sand stratum. Below the silty sand is a thick deposit of clay. Assume that the silty sand is homogeneous and isotropic. (i) Calculate q in cm/s. q / (2 marks) Analyze the pore water pressure distribution on the front of the sheet pile (at every 2m @ at points A, F and G). Given the Nd of points A, F and G are 0.5, 1.5 and 3.0 respectively. (3 marks) (iii) Analyze the pore water pressure distribution at the base of the dam. (at every 5m @ at points A, B, C, D and E). Given the Nd of points A, B, C, D and E are 5.6, 6.7, 8.0, 10.0, 13.0 respectively. (5 marks) (iv) Determine the uplift force under the dam. (2 marks) (v) Calculate the factor of safety against piping. Given Lmin=0.85m. LINIIL ULVILLIINIUS11 LVUNJL LUUL (3.rarystu 6 m 20 m -1.5m B D 1 1 F 4 m G 1 10 m 1 1 1 1 1 1 1 1 1 1 1 1 1 1 e=0.85 1 G= 2.67 Ik= 3 x 10 cm/s 1 Impervious clay FIGURE Q1 (C)