2. You are in charge of the shearing and pressing operations in a job shop. When you arrived this morning, there were se
Posted: Sun May 15, 2022 11:39 pm
2. You are in charge of the shearing and pressing operations in a job shop. When you arrived this morning, there were seven jobs with the following processing times. Job 1 2 3 4 5 6 7 Processing Time Shear Press 6 3 2 9 5 3 1 8 7 1 4 S 9 6 a) What is the makespan under the SPT dispatching rule? b) What sequence yields the minimum makespan? c) What is this makespan?