A workshop has the following jobs (A,B,C,D,E) and it is impossible to avoid some jobs being late. How would you schedule
Posted: Sun May 15, 2022 9:15 pm
A workshop has the following jobs (A,B,C,D,E) and it is impossible to avoid some jobs being late. How would you schedule the jobs in order to deliver minimum late jobs? Show workings.
Job A А. B C D m Processing time, days 4 5 3 8 2 Due date 8 14 9 7 3
Job A А. B C D m Processing time, days 4 5 3 8 2 Due date 8 14 9 7 3