Q2 (a) Produce a Pert Diagram and identify the critical path based on Table Q2(a). Table Q2(a) Description Predecessor A

Posted: Sat May 14, 2022 3:53 pm
by answerhappygod
Q2 A Produce A Pert Diagram And Identify The Critical Path Based On Table Q2 A Table Q2 A Description Predecessor A 1
Q2 A Produce A Pert Diagram And Identify The Critical Path Based On Table Q2 A Table Q2 A Description Predecessor A 1 (63.93 KiB) Viewed 47 times
Q2 (a) Produce a Pert Diagram and identify the critical path based on Table Q2(a). Table Q2(a) Description Predecessor Activity A B с D E F G Planning Analysis Interview Design Database Design Interface Implementation Testing None A B A D C,E F Estimated Time 0.5 4.0 0.5 1.0 0.5 0.5 0.5 (8 marks) (b) Draw a Gantt Chart for 10 weeks by referring to the Extreme Programing project methodology process. (9 marks)