Determine the new objective function value of the RHS of the Space Constraint increases by 5 units. Objective Function V
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Determine the new objective function value of the RHS of the Space Constraint increases by 5 units. Objective Function V
Determine the new objective function value of the RHS of the Space Constraint increases by 5 units. Objective Function Value = $51.00 Variable Cells Final Reduced Objective AllowableAllowable ValueCost Coefficientlncrease Decrease Name Variable 1 5 0 6 4 1 Variable2 3 0 7 1.5 2.67 Constraints Final Shadow Constraint Allowable Allowable ValuePrice R.H. Side Increase Decrease Name Labor 12 4 12 3 3 Wood 6.4 0 14 7.6 1E+30 12 3 12 6 1.8 Space Limit 3.2 0 10 6.8 1E+30 $47 $66 0 $51 $15 Must recalculate because increase exceeded the range of feasibility