4. (20' points) In a machine station, jobs arrive according to a Poisson process with a rate of 8 per hour. There are on
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
4. (20' points) In a machine station, jobs arrive according to a Poisson process with a rate of 8 per hour. There are on
4. (20' points) In a machine station, jobs arrive according to a Poisson process with a rate of 8 per hour. There are only two types of jobs processed in this station, Job A and Job B. The probability that a job is Job A is 2/5. If it is Job A, it takes exactly 15 minutes to process it. If it is Job B, it takes exactly 5 minutes to process it. On average, how long each job stays in the station? (Hint: M/G/1 queueing system)