by the man and the time taken only work done by the man and the vertical distance moved only 74 - (0625-W 2018-Paper 2 (
Posted: Mon May 09, 2022 1:43 pm
by the man and the time taken only work done by the man and the vertical distance moved only 74 - (0625-W 2018-Paper 2 (Extended)/2-Q11) uniform acceleration. FORCES AND ENERGY A crane on a building site lifts bricks of total mass 200 kg, initially at rest on the ground, with When the bricks are 5.0m from the ground, they have a speed of 5.0 m/s. 200x10x How much work is done during this process? А 2.5 kJ с B 10.0 kJ 12.5 kJ D 35 kJ 5- (non on CNERGY