Kanban problem Daily demand - 250 units Lead time - 1/2 day Safety stock - 14 day Kanban/container size - 50 units Calcu

Posted: Sun May 08, 2022 8:06 pm
by answerhappygod
Kanban Problem Daily Demand 250 Units Lead Time 1 2 Day Safety Stock 14 Day Kanban Container Size 50 Units Calcu 1
Kanban Problem Daily Demand 250 Units Lead Time 1 2 Day Safety Stock 14 Day Kanban Container Size 50 Units Calcu 1 (32.34 KiB) Viewed 31 times
Kanban problem Daily demand - 250 units Lead time - 1/2 day Safety stock - 14 day Kanban/container size - 50 units Calculate the number of kanbans Setup cost and time Annual demand - 31,200 units Daily demand - 120 units Daily production - 960 units Desired lot/Kanban/container/Q size – 120 units Holding cost per unit per year - $12 Setup labor cost per hour - $20 What is the setup cost and the labor setup time?