Problem 3 FA Project Management Review for Final Activity Immed Predec Optimistic Most Likely Pessimistic 1 = Expected T

Posted: Sun May 08, 2022 8:02 pm
by answerhappygod
Problem 3 Fa Project Management Review For Final Activity Immed Predec Optimistic Most Likely Pessimistic 1 Expected T 1
Problem 3 Fa Project Management Review For Final Activity Immed Predec Optimistic Most Likely Pessimistic 1 Expected T 1 (74.45 KiB) Viewed 30 times
Problem 3 FA Project Management Review for Final Activity Immed Predec Optimistic Most Likely Pessimistic 1 = Expected Time 6 = Expected Variance Critical path? a G o? ovv NKIE V W х Y m b 5 10 21 V 5 8 17 V 1 5 9 W.X 2 6 10 Y 3 8 19 Expected Completion Time Path Standard Deviation Given your work, which of the following is correctly stated? The chances of completion in 37 weeks or less is about 30.9%. The chances of completion in 37 weeks or less is about 6.7%. The chances of completion in 37 weeks or less is about 69%. The chances of completion in 37 weeks or less is about 89.4%.