--- You are the manager of a government school project. You listed the activities and gathered the data as given in Tabl
Posted: Sun May 08, 2022 4:29 pm
--- You are the manager of a government school project. You listed the activities and gathered the data as given in Table G Table G Immediate Activity Predecessor E[T(Weeks) A 5 B 6 А 4 D A 3 E А 1 F E 4 G D&F 14 H B&C 12 G&H 2 لما كان If you assume that the expected duration of the project in Table G is 26 weeks and the standard deviation of the critical path is 2.05 weeks, what is the latest date to start this project to have at least a 95% chance of completion by December 24,2022, assuming that work is done every week, from start to finish? Select one: a. December 1 O b. November 30 O c. November 27 d. November 24