A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th

Posted: Sun May 08, 2022 4:29 pm
by answerhappygod
A task has an
optimistic completion time of 6 days, a most likely time of 10
days, and a pessimistic time of 14 days. The expected task duration
is:
10.5 days
11.5 days
9.5 days
12 days
11 days
10 days