Page 1 of 1

How would I build the MRP Table in this example. Detailed explanation would be very helpful thank you.

Posted: Sun May 08, 2022 9:06 am
by answerhappygod
How Would I Build The Mrp Table In This Example Detailed Explanation Would Be Very Helpful Thank You 1
How Would I Build The Mrp Table In This Example Detailed Explanation Would Be Very Helpful Thank You 1 (128.93 KiB) Viewed 31 times
MRP Exercise 3 Bill of materials A (1) Code A B ะก D E TO O Parts 1 1 2 1 4. Lead time 1 week 1 week 2 weeks 1 week 3 weeks B (1) C (2) N+ D (1) E (4) (the number in parentheses is the number of parts) Build MRP table taking into account that the final product A required is 100 units in week 6 and considering that there are 50 units available inventory of product B in week 5 and 20 units of product C are received at week 4 7