A A tertiary institution is planning for a project to encourage its staff and students to participate in a public runnin

Posted: Sun May 08, 2022 9:01 am
by answerhappygod
A A Tertiary Institution Is Planning For A Project To Encourage Its Staff And Students To Participate In A Public Runnin 1
A A Tertiary Institution Is Planning For A Project To Encourage Its Staff And Students To Participate In A Public Runnin 1 (56.5 KiB) Viewed 45 times
A A Tertiary Institution Is Planning For A Project To Encourage Its Staff And Students To Participate In A Public Runnin 2
A A Tertiary Institution Is Planning For A Project To Encourage Its Staff And Students To Participate In A Public Runnin 2 (42.76 KiB) Viewed 45 times
A A tertiary institution is planning for a project to encourage its staff and students to participate in a public running event to be held in a mn this year. Assume the current time is day . The project involves a series of inter-related activities with the estimated activity duration time given in the following table: Activity Immediate Time Special requirement Label Description Predecessors days) А Registration 4 Exactly 7 days in between each training day. i.e. all fall B Training programme 4 on the same weekday, the whole training programme lasts for 4 weeks С Briefing by coach At least 12 days А 2 (including preparation) after activity A D Distribution of uniform BC 5 E Arranging baggage AD 7 handling services F Organize cheer group CD 4 G Race day D. EF 1 Fixed on day 50 to start Reunion and prize H At least 7 days presentation (including G 2 preparation) after activhy G a) Draw the project network. (8 marks) b) Determine the earliest start time (ES), earliest finish time (EF), latest start time (LS) and latest finish time (LF) for each activity in the network diagram in (a). (8 marks) c) What is the shortest project duration time? (Hint: Consider the relevant times of the last activity and the first activity in (b).) (2 marks) d) What is the latest day that the project should start? (1 mark)
Reunion and prize presentation (including preparation) H G At least 7 days after activity G 2 (8 marks) a) Draw the project network b) Determine the earliest start time (ES), earliest finish time (EF). latest start time (LS) and latest finish time (LF) for each activity in the network diagram in (a). (8 marks) c) What is the shortest project duration time? (Hint: Consider the relevant times of the last activity and the first activity in (b).) (2 marks) d) What is the latest day that the project should start? (1 mark) e) Assume that the project starts on the latest start day in (d), which activities have non-zero slack and how much? (3 marks) f) Based on the latest project start day in (d), determine the critical path. (3 marks)