A given project activity has the following time estimates: a = 5 b = 34 m = 19 What is the variance ( σ2 ) of this proje
Posted: Thu May 05, 2022 9:42 am
A given project activity has the following time estimates:
a = 5
b = 34
m = 19
What is the variance ( σ2 ) of this project activity's
estimated duration? (Round to 2 decimal places)
a = 5
b = 34
m = 19
What is the variance ( σ2 ) of this project activity's
estimated duration? (Round to 2 decimal places)