The lead time for the replenishment of a part is 6 hours, demand is 18 per hour, safety stock is 13% of demand, and the

Posted: Thu May 05, 2022 9:41 am
by answerhappygod
The Lead Time For The Replenishment Of A Part Is 6 Hours Demand Is 18 Per Hour Safety Stock Is 13 Of Demand And The 1
The Lead Time For The Replenishment Of A Part Is 6 Hours Demand Is 18 Per Hour Safety Stock Is 13 Of Demand And The 1 (36.41 KiB) Viewed 37 times
The lead time for the replenishment of a part is 6 hours, demand is 18 per hour, safety stock is 13% of demand, and the container size is 15 units. How many kanban sets are needed? 4 8 9 11 10