2. Given the following MPS and bills of capacity, calculate the estimated capacity requirements for Work Center 100, 200
Posted: Thu May 05, 2022 9:18 am
2. Given the following MPS and bills of capacity, calculate the estimated capacity requirements for Work Center 100, 200 and 300 using the capacity bills technique, and fill out the table below. Master production schedule (in units) Period End Product 2 3 A 20 30 30 B 15 20 20 Bill of Capacity: End Product A Work Center Total Time/Unit 100 0.25 200 0.25 300 0.25 Total Time/Unit 0.75 Estimated Capacity Requirements B Total Time/Unit 0.3 0.5 0.2 1
Work Center 100 200 300 Total Required Capacity 1 Period 2 3
Work Center 100 200 300 Total Required Capacity 1 Period 2 3