b) Examine the Linear schedule with sequential activities A, B and C can be interrupted at integer work or time units an
Posted: Wed May 04, 2022 9:31 am
b) Examine the Linear schedule with sequential activities A, B and C can be interrupted at integer work or time units and that any segments of activities must always keep buffer of at least 1 day between them to answer the questions see figure below: Time 4 3 2 1 Work 1 2 3 4 5 6 1) Can deliberate interruptions within activities of a linear schedule help minimizing its total project duration? If so, WHY: If NOT Why? 2) Which activities should be interrupted? What is the minimum duration of the project. 18 7 99