Carol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average
Posted: Wed May 04, 2022 8:20 am
Carol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average inventory turnover of only 12 times per year. He has therefore determined that he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip: $30 per hour $13 per unit Setup labor cost Annual holding cost Daily production Annual demand Desired lot size 976 units/8 hour day 32,400 (270 days each x daily demand of 120 units) 122 units (one hour of production) To obtain the desired lot size, the set-up time that should be achieved = minutes (round your response to two decimal places).