A project has been defined to contain the following activities, along with their time estimates for completion: Time Est
Posted: Wed May 04, 2022 8:13 am
A project has been defined to contain the following activities, along with their time estimates for completion: Time Estimates (weeks) Activity a m b Immediate Predecessor A 1 7 B 2 7 с 3 6 D 6 14 E 3 12 F 6 S 16 B. C G 5 6 E. F a. Calculate the expected time and the variance for each activity. b. Draw the critical path diagram. e. Show the early start, early finish times, and late start, late finish times. d. Show the critical path. e. What is the probability that the project can be completed in 34 weeks? f: what is the probability that the project can be completed between 20 and 34 weeks? g: what is the probability that the project can be completed after week 30? You need to use the NORM.S.DIST() formula available in excel to determine the probability of z-value. Make sure, you choose TRUE for the cumulative option. 4 6 4 12 6 | < 0