The following table provides crash data for Problem #1 with normal activity times considered to be deterministic. How mu
Posted: Mon May 02, 2022 4:12 pm
The following table provides crash data for Problem #1 with normal activity times considered to be deterministic. How much would it cost to complete the project in 26 weeks? What will be the critical path for the project? Identify each crashing activity, the resulting critical path and the cost. Activity a b C d A Activity Time (weeks) Normal Crash 9 7 11 9 7 5 10 8 1 1 5 3 6 5 3 3 1 1 2 2 8 6 Activity Cost Normal Crash $4,800 $ 6,300 9,100 15,500 3,000 4,000 3,600 5,000 0 0 1,500 2,000 1,800 2,000 0 0 0 0 0 0 5,000 7,000 - ORO ON-ww-Con h j k