8. QUESTION EIGHT Choose the correct statement below (2 marks) A) The critical path consumes the maximum time B) The act

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

8. QUESTION EIGHT Choose the correct statement below (2 marks) A) The critical path consumes the maximum time B) The act

Post by answerhappygod »

8 Question Eight Choose The Correct Statement Below 2 Marks A The Critical Path Consumes The Maximum Time B The Act 1
8 Question Eight Choose The Correct Statement Below 2 Marks A The Critical Path Consumes The Maximum Time B The Act 1 (48.6 KiB) Viewed 33 times
8. QUESTION EIGHT Choose the correct statement below (2 marks) A) The critical path consumes the maximum time B) The activities connecting the events having zero slack lie on the critical path, The difference of the latest occurrence time and earliest expected time is called slack D) All above 9. QUESTION NINE If the optimistic time, most likely time and pessimistic time for an activity A are 40,60 and 80 hours respectively and for activity B are 50,55 and 90 hours respectively, then A) Expected time of activity A is greater than expected time for activity B B) Expected time of activity B is greater than the expected time of activity A C) Expected time of both activities A and B are the same D) None of the above (2 marks) (2 marks) 10. QUESTION TEN Indicate the correct statement from the following: A) Optimistic time estimates refer to activities B) Pessimistic time estimates refer to activities C) Most likely time estimates refer to activities D) All above (2 marks) 11. QUESTION ELEVEN In resources levelling A) Total duration of project is reduced B) Total duration of the project is increased C) Uniform demand of resources is achieved D) Cost of project is controlled