Page 1 of 1

WASTEWATER ENGINEERING

Posted: Mon May 02, 2022 10:54 am
by answerhappygod
WASTEWATER ENGINEERING
Wastewater Engineering 1
Wastewater Engineering 1 (27.44 KiB) Viewed 20 times
3. The details of a new developed area are given below: Premise Details Houses 2,000 units Hotel 2 hotels, 100 rooms hotel (area = 1,200 m) Hospital 1 hospital, 300 beds (area = 3.000 m) Bus terminal 2 terminals, 16 bays/terminal Shopping mall (3 levels) 1 mall. 5,000 customer/day (floor area = 2,500 m) a. Estimate the average and peak water consumption of the area. b. If the STP was then designed suitable for 150% of the PE, how many houses can be added?