Marle Construction enters into a contract with a customer to build a warehouse for €950,000 on March 30, 2021 with a per
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Marle Construction enters into a contract with a customer to build a warehouse for €950,000 on March 30, 2021 with a per
Marle Construction enters into a contract with a customer to build a warehouse for €950,000 on March 30, 2021 with a performance bonus of €50,000 if the building is completed by July 31, 2021. The bonus is reduced by €10,000 each week that completion is delayed. Marle commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 65% August 7, 2021 25% August 14, 2021 5% August 21, 2021 5% What is the transaction price for this contract?