A site is to be graded such that a level building pad will be installed at an elevation of 110 feet. Cross-sections of t
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A site is to be graded such that a level building pad will be installed at an elevation of 110 feet. Cross-sections of t
A site is to be graded such that a level building pad will be installed at an elevation of 110 feet. Cross-sections of the existing ground are provided above. Section A and Section B are 150 feet apart. Note that the vertical scale is different from the horizontal scale; this is often done in engineering to exaggerate the variation in the vertical direction. How much fill is needed between Section A and Section B? Proposed building pad Fill 110 Existing ground Section A 100 90 (Datum) 0 25 50 75 100 125 150 175 110 Section B 100 90 0 (Datum) 25 50 75 100 125 150 175
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!