For a water purification plant of capacity 15000 m’/d shown in figure determine: 0.30 m 0.40 ml 9 m 2.70 m PLAN 0.40 m S
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
For a water purification plant of capacity 15000 m’/d shown in figure determine: 0.30 m 0.40 ml 9 m 2.70 m PLAN 0.40 m S
For a water purification plant of capacity 15000 m’/d shown in figure determine: 0.30 m 0.40 ml 9 m 2.70 m PLAN 0.40 m Sec A-A Flocculator Sed tank 1. Quantity of alum added (ton/month) if the rapid mixing tank will blend 30 mg/L of alum with the flow. 2. Design the flocculator tank (basin dimensions, power requirements, paddle configuration),if o = 4 rev/min G-value = 31 sec !, Gt = 3 x 104 and the depth of tank is 3.5 m. 3. Design the sedimentation tank (tank dimensions) and checks of (horizontal velocity, over flow weir and over flow rate) if depth of tank is 4.0 m and detention time 3.0 hrs.