QUESTION 29 Which of these is NOT an essential characteristic to perform analysis using the Critical Path Method? The jobs must all have similar cycle times. Jobs can be started and stopped independently of each other, within a given sequence. The jobs must be performed in technological sequence. The jobs must be well defined.