Summary of Scenario Data for Project Completion Time (months) Average 45.35 Maximum 60.42 Minimum 33.60 Std. Dev. 4.25 R

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Summary of Scenario Data for Project Completion Time (months) Average 45.35 Maximum 60.42 Minimum 33.60 Std. Dev. 4.25 R

Post by answerhappygod »

Summary of Scenario Data for
Project Completion Time (months)
Average
45.35
Maximum
60.42
Minimum
33.60
Std. Dev.
4.25
Range
26.82
Median
49.76
90th Percentile
57.85
80th Percentile
56.34
20th Percentile
36.40
10th Percentile
35.00
1) What is the expected duration of the project?
60.42
49.76
45.35
33.60
26.82
2) What is the probability that the project
will not be completed within 36
months?
< 25%
>= 25% and < 50%
>= 50% and < 75%
>= 75%
3) There is a 50-50 chance that the project will be completed
within
60.42
49.76
45.35
33.60
26.82