How long is the project shown in the diagram below expected to last? с A 0 E B D 2. 4 Activity Expected Time (days) Stan
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
How long is the project shown in the diagram below expected to last? с A 0 E B D 2. 4 Activity Expected Time (days) Stan
How long is the project shown in the diagram below expected to last? с A 0 E B D 2. 4 Activity Expected Time (days) Standard Deviation (days) А 28 3 В 12 2 с 25 3 D 37 4 E 35 2 F 19 1 G 20 2 0 < 65 O >= 65 and < 70 O >= 70 and < 75 O >= 75