“Let’s assume a 12-month railway project that is planned to spend $3M per month for a total budget at completion of $36M

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

“Let’s assume a 12-month railway project that is planned to spend $3M per month for a total budget at completion of $36M

Post by answerhappygod »

“Let’s assume a 12-month railway project that is planned to
spend $3M per month for a total budget at completion of $36M. The
project is 2 months along and according to the actual cost is
underspent by 50% compared to the planned value. We could assume
therefore that the project is going well because it’s costing less
than planned. But after 2 months of work, 10 % of work has been
completed”