Failures or missteps as a result of implementation during the Plan Do Check Adjust/Act (PDCA) Cycle should be treated in which of the following ways?
As an unfortunate by-product of the "Do" step
As a reason to slow down and lengthen the "Plan" step
As a good source of information for the "Adjust (Act)" step
As an avoidable risk during the "Check (Study)" step
Failures or missteps as a result of implementation during the Plan Do Check Adjust/Act (PDCA) Cycle should be treated in
-
- Site Admin
- Posts: 899566
- Joined: Mon Aug 02, 2021 8:13 am