As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)
Remove or change selected Product Backlog items.
The Developers work overtime during this Sprint.
Cancel the Sprint.
The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
Recruit additional Developers before the work can begin.