What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later?
A. Accrual
B. Forecast
C. Commitment
D. Baseline
What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting late
-
- Site Admin
- Posts: 895507
- Joined: Mon Aug 02, 2021 8:13 am
What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting late
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying! For more answers search our other sites: AnswerAccurate HomeworkAnswerHelp QuestionAnswerDump and Snapsterpiece