Over the course of several Sprints, the relationship between the Product Owner and the Development team has suffered. Th

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

Over the course of several Sprints, the relationship between the Product Owner and the Development team has suffered. Th

Post by answerhappygod »

Over the course of several Sprints, the relationship between the Product Owner and the Development team has suffered. The Development Team is upset with the Product Owner for the constantly changing the upcoming items for the product. The Product Owner is upset with the Development Team for changing the work that needs to be done during the Sprint.
What should Steven, the Scrum Master, do?

A. During the Sprint Retrospective, ask the Product Owner and the Development Team to address the issues. Have the Team discuss why the changes occur and what impact they have on the value of the product.
B. The Scrum Master's responsibility is to ensure the Development Team has a stable velocity. Any changes that negatively impact the team's velocity will be rejected by the Scrum Master.
C. Take the time between Sprints to organize a team building session to rebuild the relationship.
D. Explain to the Development Team that the Product Owner is accountable for flow of value and needs to be followed in order to maximize the value delivered.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply