Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

The CEO asks the Development Team to add a `very important` item to a Sprint that is in progress. What should the Develo

Post by answerhappygod »

The CEO asks the Development Team to add a `very important` item to a Sprint that is in progress. What should the Development Team do?

A. Add the item to the current Sprint and drop an item of equal size.
B. Add the item to the current Sprint without any adjustments.
C. Inform the Product Owner so he/she can work with the CEO.
D. Add the item to the next Sprint.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.